Key facts
- Licensed at any value
- Plumbing, gasfitting and electrical work.
- Certificates
- Plumbing compliance certificate over $750, and for all gasfitting; Certificate of Electrical Safety for electrical work.
- Registered builder
- Needed when the whole job costs more than $10,000.
- Structural changes
- Removing or moving a wall needs a registered practitioner and a building permit.
1Before anything is removed
Finalise the layout and appliances first, because the positions of the sink, cooktop and oven decide where pipes, gas and power must go. Check the age of the house: wall linings and old vinyl in pre-1990 kitchens may contain asbestos.
If the plan involves taking out a wall to open the kitchen to a living area, that is structural work. Consumer Affairs Victoria states that structural work must be done by a registered practitioner regardless of cost and requires a building permit.
2The sequence
- Disconnect. A plumber caps water and gas; an electrician makes circuits safe.
- Strip out cabinets, benchtops, splashback and flooring.
- Rough-in. Plumber, gasfitter and electrician run new services in the open walls.
- Make good. Plaster is patched and sanded.
- First paint. Ceiling and walls get their undercoat and first coat while the room is empty.
- Flooring, if it runs under the cabinets.
- Cabinets, then the benchtop template and installation.
- Splashback and tiling.
- Fit-off. Plumber connects sink, dishwasher and gas; electrician fits appliances, switches and lights.
- Final paint. Top coat on walls, then trims and touch-ups.
3Why the painter comes twice
Painting an empty room is quick and clean, so the first coats go on before cabinets. The final coat waits until every other trade has finished, because installers mark walls and electricians cut holes. A single visit at the end means cutting in around every cabinet edge; a single visit at the start means the finish is damaged before you move in.
In kitchens, choose a washable finish for walls and a harder enamel for doors and trims, and make sure new plaster is sealed before it is painted.
4Paperwork to keep
Collect the plumbing compliance certificate, the Certificate of Electrical Safety and appliance warranties. If the job cost more than $10,000, you should also hold a signed major domestic building contract. From 1 July 2026, jobs over $20,000 also require Home Warranty insurance cover. Details are in contracts, deposits and insurance.
?Readers ask
How long is a kitchen out of action?
It depends mostly on the benchtop, which is measured after cabinets are installed and then manufactured. Ask the supplier for that lead time before you set a date.
Can I keep the old layout and save money?
Yes. Leaving the sink, cooktop and oven where they are avoids most of the plumbing, gas and electrical rough-in.
Does replacing cabinets need a building permit?
Non-structural replacement is commonly exempt, but all building work needs a permit unless an exemption applies. Check with a building surveyor or your council.
Sources
- Consumer Affairs Victoria: Home improvements costing $10,000 or less (checklist)
- Building and Plumbing Commission: Plumbing compliance certificates
- Energy Safe Victoria: Certificates of electrical safety
- Building and Plumbing Commission: When is a building permit required?
- Consumer Affairs Victoria: Domestic Building Consumer Guide
Drop Sheet publishes general information for Victoria. It is not legal, building or health advice, and rules change. Confirm anything that matters with the official source or a qualified professional.