Kitchen renovation: the order of work, and why painters come twice

Kitchens go wrong when trades arrive in the wrong order. A cabinet maker waiting on a plumber costs money; a painter working around an electrician costs the finish.

Kitchen mid-renovation with new cabinet carcasses and capped pipes at the wall

Key facts

Licensed at any value
Plumbing, gasfitting and electrical work.
Certificates
Plumbing compliance certificate over $750, and for all gasfitting; Certificate of Electrical Safety for electrical work.
Registered builder
Needed when the whole job costs more than $10,000.
Structural changes
Removing or moving a wall needs a registered practitioner and a building permit.

1Before anything is removed

Finalise the layout and appliances first, because the positions of the sink, cooktop and oven decide where pipes, gas and power must go. Check the age of the house: wall linings and old vinyl in pre-1990 kitchens may contain asbestos.

If the plan involves taking out a wall to open the kitchen to a living area, that is structural work. Consumer Affairs Victoria states that structural work must be done by a registered practitioner regardless of cost and requires a building permit.

2The sequence

  1. Disconnect. A plumber caps water and gas; an electrician makes circuits safe.
  2. Strip out cabinets, benchtops, splashback and flooring.
  3. Rough-in. Plumber, gasfitter and electrician run new services in the open walls.
  4. Make good. Plaster is patched and sanded.
  5. First paint. Ceiling and walls get their undercoat and first coat while the room is empty.
  6. Flooring, if it runs under the cabinets.
  7. Cabinets, then the benchtop template and installation.
  8. Splashback and tiling.
  9. Fit-off. Plumber connects sink, dishwasher and gas; electrician fits appliances, switches and lights.
  10. Final paint. Top coat on walls, then trims and touch-ups.

3Why the painter comes twice

Painting an empty room is quick and clean, so the first coats go on before cabinets. The final coat waits until every other trade has finished, because installers mark walls and electricians cut holes. A single visit at the end means cutting in around every cabinet edge; a single visit at the start means the finish is damaged before you move in.

In kitchens, choose a washable finish for walls and a harder enamel for doors and trims, and make sure new plaster is sealed before it is painted.

4Paperwork to keep

Collect the plumbing compliance certificate, the Certificate of Electrical Safety and appliance warranties. If the job cost more than $10,000, you should also hold a signed major domestic building contract. From 1 July 2026, jobs over $20,000 also require Home Warranty insurance cover. Details are in contracts, deposits and insurance.

?Readers ask

How long is a kitchen out of action?

It depends mostly on the benchtop, which is measured after cabinets are installed and then manufactured. Ask the supplier for that lead time before you set a date.

Can I keep the old layout and save money?

Yes. Leaving the sink, cooktop and oven where they are avoids most of the plumbing, gas and electrical rough-in.

Does replacing cabinets need a building permit?

Non-structural replacement is commonly exempt, but all building work needs a permit unless an exemption applies. Check with a building surveyor or your council.